APLIKASI INTERPRETIVE STRUCTURAL MODELING (ISM) PADA FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI DI SURABAYA

Authors

  • Eric Cahyadi Halim student Universitas Kristen Petra
  • Andi Andi Magister Teknik Sipil
  • Jani Rahardjo

DOI:

https://doi.org/10.9744/duts.8.1.60-77

Keywords:

delay, risk, residental construction, DEMATEL, ISM

Abstract

 Construction projects run the risk of not conforming to the initial expectations of development. It is very difficult to estimate the time of a project because a project is not repetitive, there are different challenges in each development project. Delay in completing a project will cause waste in the form of overtime and overbudget. This research was conducted using judgment sampling to 5 respondents who were expert contractors. The objectives to be achieved through this research are to identify the dominant factors causing delays in a residental project using the Decision Making Trial and Evaluation Laboratory (DEMATEL) method and modeling the relationship between the factors that cause delays in residential construction projects using the Interpretive Structural Modeling (ISM) method. The result of this research is the existence of 8 levels of sub-factor hierarchical structure which becomes the framework for contractors and project owners to reduce the risk of delays in residential construction projects. The dominant causes of delays in project development are design changes during construction, late delivery of materials, late approval of work drawings, late payments, and inappropriate work methods.

References

Abdul-Rahman, H., Berawi, M. A., Berawi, A. R., Mohamed, O., Othman, M., & Yahya, I. A. (2006). Delay Mitigation in the Malaysian Construction Industry. Journal of Construction Engineering and Management, 132(2), 125-133.

Al-Momani, A. H. (2000). Construction Delay: a Quantitative Analysis. International Journal of Project Management, 18(1), 51-59.

Alzebdeh, K., Bashir, H. A., & Al Siyabi, S. K. (2015). Applying Interpretive Structural Modeling to Cost Overruns in Construction Projects in the Sultanate of Oman. The Journal of Engineering Research (TJER), 12(1), 53-68.

Andi, A., Lalitan, D., & Loanata, V. R. (2010). Owner and Contractor Perceptions Toward Factors Causing Delays in Structural and Finishing Works. Civil Engineering Dimension, 12(1), 8-17.

Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995). Causes of Delay in Large Building Construction Projects. Journal of Management in Engineering, 11(2), 45-50.

Collis, J., & Hussey, R. (2003). Business Research. Palgrave Macmillan.

Faridi, A. S., & El‐Sayegh, S. M. (2006). Significant Factors Causing Delay in the UAE Construction Industry. Construction Management and Economics, 24 (11), 1167-1176.

Hamzah, N., Khoiry, M. A., Arshad, I., Tawil, N. M., & Ani, A. C. (2011). Cause of Construction Delay-Theoretical Framework. Procedia Engineering, 20, 490-495.

Hassan, H., Mangare, J. B., & Pratasis, P. A. (2016). Faktor–Faktor Penyebab Keterlambatan pada Proyek Konstruksi dan Alternatif Penyelesaiannya (Studi kasus: di Manado Town Square III). Jurnal Sipil Statik, 4(11), 657-664.

Hendrickson, C., & Au, T. (2000). Project Management for Construction: Fundamental Concepts for Owners. Pittsburgh: Prentice Hall.

Janes, F. R. (1988). Interpretive Structural Modelling: a Methodology for Structuring Complex Issues. Transactions of the Institute of Measurement and Control, 10 (3), 145–154. doi:10.1177/014233128801000306

Kaliba, C., Muya, M., & Mumba, K. (2009). Cost Escalation and Schedule Delays in Road Construction Projects in Zambia. International Journal of Project Management, 27 (5), 522-531.

Kementerian Keuangan Republik Indonesia. (2019). Anggaran Pendapatan dan Belanja Negara (APBN) 2019. Diakses dari https://www.kemenkeu.go.id/ apbn2019.

Listanto, N., & Hardjomuljadi, S. (2019). Analisis Faktor Penyebab Keterlambatan Pembayaran Kontraktor kepada Subkontraktor pada Proyek Gedung Bertingkat. Konstruksia, 10(1), 59-72.

Messah, Y. A., Widodo, T., & Adoe, M. L. (2013). Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstuksi Gedung di Kota Kupang. Jurnal Teknik Sipil, 2 (2), 157-168.

Oberlender, G. D., & Oberlender, G. D. (2000). Project Management for Engineering and Construction. New York: McGraw-Hill.

Peneliting, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors Influencing Construction Time and Cost Overruns on High-Rise Projects in Indonesia. Construction Management & Economics, 15(1), 83-94.

Sambasivan, M., & Soon, Y. W. (2007). Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Management, 25(5), 517-526.

Tavakolan, M., & Etemadinia, H. (2017). Fuzzy Weighted Interpretive Structural Modeling: Improved Method for Identification of Risk Interactions in Construction Projects. Journal of Construction Engineering and Management, 143(11), 04017084.

Toor, S.-U.-R. and Ogunlana, S.O. (2010). Beyond the “Iron Triangle”: Stakeholder Perception of Key Performance Indicators (KPIs) for Large-Scale Public Sector Development Projects. International Journal of Project Management, 28, 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005

Zhou, D. Q., Zhang, L., & Li, H. W. (2006). A Study of the System's Hierarchical Structure Through Integration of DEMATEL and ISM. In International Conference on Machine Learning and Cybernetics 2006 (pp. 1449-1453).

Downloads

Published

2021-04-30

How to Cite

Halim, E. C., Andi, A., & Rahardjo, J. (2021). APLIKASI INTERPRETIVE STRUCTURAL MODELING (ISM) PADA FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI DI SURABAYA. Dimensi Utama Teknik Sipil, 8(1), 60–77. https://doi.org/10.9744/duts.8.1.60-77

Issue

Section

Articles