Model Proyeksi Dan Optimalisasi Cash Flow Multi Proyek

Authors

  • Resela Irpiena Magister Teknik Sipil
  • Ratna Setyawardani Alifen Magister Teknik Sipil Universitas Kristen Petra
  • Herry Pintardi Chandra Magister Teknik Sipil Universitas Kristen Petra

DOI:

https://doi.org/10.9744/duts.3.2.1-8

Keywords:

model, schedule, cash flow, multi project, optimization.

Abstract

This study aims to create an integrated system that has the ability to project the schedule and cash flow of a multi project situation for construction companies, while optimizing them so that a more efficient schedule and financial planning is achieved. In this study, an efficient construction planning refers to a schedule combination that generates a cash flow with minimum overdraft for the company.

This study focuses on utilizing floats from non-critical activities in initial or as-planned schedule. Iteration on the floats is done with evolutionary algorithm optimization method using projects’ durations and credit limit as constraints. The result is a combination of multi project schedules which generates the least amount of overdraft throughout the fiscal year to achieve minimum loans of thecompany.